REPORT FOR THE WEST END WARD - WEEK COMMENCING MONDAY 9 SEPTEMBER 2024
Blinshall Street (Douglas Street to 50 metres south) - closed until December 2024 for construction works.
Douglas Street (Blinshall Street to Brown Street) - temporary traffic lights until December 2024 for construction works.
Brown Street (south of Douglas Street) - closed until December 2024 for construction works.
Seafield Road, Dundee - closed from its westmost end (in cul-de-sac) extending for a distance of no more than 20 metres in an easterly direction to facilitate a site access for a new housing development until November 2025.
Scottish and Southern Energy Network Elmwood Cable Renewal Scheme – rolling road closures from Monday 24 June for 28 weeks – West End roads affected :
+ City Road (Blyth Street to Milnbank Gardens) – closed until Monday 9 September;
+ City Road/Tullideph Road junction – temporary traffic lights from Sunday 8 September for 2 weeks; and
+ Tullideph Road (City Road to Ancrum Road) – closed westbound from Sunday 8 September for 5 weeks.
Riverside Avenue/Dykes of Gray Road (at Swallow roundabout) - closed Monday to Friday overnight (7.00pm to 7.00am) from Monday 1 July for 11 months for junction improvement works.
A90 Kingsway (at Swallow roundabout) – overnight (7.30pm to 6.30am) contraflow for 10 months for third party works.
Brewery Lane – give and take from Monday 9 September for one week for street lighting works.
Kirsty Semple Way (at Tom McDonald Avenue) – temporary traffic lights from Monday 9 September for one week for fibre ducting works.
West Park Road – closed between Blackness Road and Beechwood Terrace from Monday 9 September for one week for carriageway resurfacing. There will be intermittent temporary traffic lights on Blackness Road during this time to facilitate works vehicles for accessing/egressing the site.
Forthcoming Roadworks
Perth Road (Hawkhill to Shepherds Loan) – closed eastbound from 9.00am on Tuesday 17 September to 6.00am on Wednesday 18 September for Scottish Water work.
Lower Pleasance (Lochee Road to Brewery Lane) – closed from Wednesday 18 September for 4 weeks for Scottish and Southern Energy Network work.
Blackness Road (at Glamis Road) – temporary traffic lights from 9.00am on Wednesday 18 September to 6.00am on Thursday 19 September for Scottish Water work.
Hawkhill (Perth Road to Bellfield Street) – off‑peak stop/go traffic control from Monday 23 September to Friday 27 September for carriageway lining works.
Hawkhill (Bellfield Street to Hunter Street) – off‑peak lane closures from Monday 30 September to Friday 4 October for carriageway lining works.
Sycamore Place - closed for its entire length from Monday 23 September for 5 days for carriageway resurfacing.
Perth Road (at Union Place) – temporary traffic lights from Tuesday 24 September for one week for Scottish Water work.
Rosebery Street (Pitfour Street to Cleghorn Street) – closed Monday 30 September for 8 days for Scottish Water work.