REPORT FOR WEST END WARD - WEEK COMMENCING MONDAY 14 AUGUST 2023
Brown Street (south of Douglas Street) - closed for 13 months until May 2024 for construction works.
Greenmarket – closed for electricity works at its junction with West Marketgait (northbound exit lane only) commencing Monday 14 August for 2 weeks.
Forthcoming Roadworks
Seafield Road, Dundee. Closed from its westmost end (in cul de sac) extending for a distance of no more than 20 metres in an easterly direction to facilitate a site access for a new housing development. Commencing Tuesday 22 August for 15 months.