Greenmarket (at MSCP) – temporary traffic lights for 9 days for electric charging point power installation.
Tait’s Lane – closed from Tuesday 25 January for 2 weeks for footway resurfacing.
Perth Road (Blackness Avenue to Windsor Street) – closed westbound (9.30 am to 3.30 pm) from Monday 24 January for 10 days for Road Safety works.
Riverside Approach (Riverside Drive to Magdalen Yard Road) – closed overnight (10.00 pm – 9.00 am) on Saturday 29 January for Scottish Gas Network works.
Forthcoming Roadworks
Lochee Road (Smellies Lane to North Marketgait) – closed east bound from Monday 7 February for 4 days for VM work.