DUNDEE CITY COUNCIL - WEEKLY ROAD REPORT
REPORT FOR WEST END WARD WEEK COMMENCING MONDAY 8 MAY 2017
Riverside Esplanade/Riverside Drive (Tay Road Bridge off ramp to 75m along Riverside Drive) – westbound nearside lane closure for 28 weeks to facilitate V&A construction works.
SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street for 11 weeks.
Riverside Approach (Roseangle/Magdalen Yard Road to Riverside Drive) – closed for one week for carriageway resurfacing works.
Perth Road (at Farington Street) – temporary traffic lights until Tuesday 9 May for Hydro cable fault repairs.
Perth Road (at Farington Street) – temporary traffic lights from Friday 12 to Monday 15 May for BT manhole repairs.
West Marketgait (at Nethergate) – off-peak offside lane closures from Tuesday 9 May for 3 days for traffic signal ducting works.
Wright Avenue – off-peak temporary traffic lights on Friday 12 May for telecommunications works.