Thursday, 26 February 2015

Progress with the pedestrian bridge at Seabraes

Further to my previous updates about the new pedestrian bridge at Seabraes, across the rail line to Riverside, I recently asked the City Engineer for an update on progress with the bridge's construction.

He has responded positively as follows :

"The project is progressing well and is on programme. 

You may have seen that the bridge steelwork has been delivered to site and is in the process of being fabricated for a single lift into place mid-April. 

The works‎ are programmed for completion and opening mid May 2015."

See photo below of the bridge steelwork :