With thanks to the Tay Road Bridge Manager, here is the monthly update on the Dundee City Waterfront Development works and how this has impacted on traffic on the bridge:
Contract 3 – Sir Robert McAlpine (SRM)
Progress March 2014
There have been no major issues affecting traffic accessing and exiting the bridge despite Customs House on ramp being reduced to one lane for the month of March
Road surfacing and white lines to ramps
Installation of parapets
Installation of expansion joints
Preparation for relocation of traffic control barriers, lights and warning wig-wags on plaza area
Planned Works – April 2014
Completion of all outstanding surfacing, white lines, crash cushions, traffic control measures on plaza, relocation of Police Automatic Number Plate recognition cameras and ancillary works to allow the works to completely open on Friday 18th April.