Wednesday, 18 August 2010

Thomson Street - latest

Further to my update last month on the impending gas and water work that will start next week in Thomson Street, I have received the following update from Scottish Water today :

Our contractors, Morrisons, will begin a short programme of work to replace more than 300 metres of ageing water mains in Thomson Street, Dundee. Work is planned to start on 23 August and last for approximately 4 weeks.

Our engineers will use the latest slip-lining method, in order to keep disruption to a minimum. Slip-lining involves easing the new durable, plastic pipe into the existing water main, which in itself provides a robust outer protection.

In order to keep traffic disruption to a minimum, we will only be working one section at a time. The letter below has been sent to local residents and further notices will be sent regarding the planned interruptions to supply :

Dear Customer,

Further to my letter dated 29th July 2010, I am writing to you as promised with an update on the work to replace the water mains in Thomson Street.

How this affects you
Work is planned to start on 23rd August and last for approximately 4 weeks. During this time it will be necessary to close Thomson Street to allow all work to be carried out as safely as possible. Work will be carried out in 3 sections and access will be maintained for 2 of the 3 sections of Thomson Street at any one time.

Work at section 1 will start on 23rd August followed by sections 2 and 3. Details of each of the 3 sections are as follows:

• Section 1 – Top of Thomson Street to 22/24a Thomson Street
• Section 2 – 22/24a Thomson Street to 46d Thomson Street
• Section 3 – 46d Thomson Street to Bottom of Thomson Street

Each section will take approximately 10 days to complete and an interruption to your water supply is required to connect your property to the new water main. Please be aware that the duration of each section may change depending on the progress of the work.

What do you need to know
Due to the nature of the water network, some properties will require more than 1 interruption. You will be given 48hrs notice of any supply interruptions.

Working hours will be Monday to Friday 07.30 to 18.00 hrs. No weekend working is anticipated at this stage.

Our contractor Morrison Construction will also assist with bin collections for each section when it is closed for our work. Bins should be taken out as normal where Morrison Construction will assist with moving bins to appropriate areas for collection.

Ally Mitchell from Morrison Construction will be available during working hours to provide assistance and can be contacted on 07809 530642. Any out of hours issues, please call our Customer Helpline detailed below.

We will make all reasonable efforts to minimise disruption.

We would like to thank you for your understanding and cooperation while we complete these essential works. If you have any questions or requirements about Scottish Water or the project, please call our Customer Helpline on 0845 601 8855 quoting reference “Capital/400797/MRN"