DUNDEE CITY COUNCIL - ROAD REPORT FOR THE WEST END
REPORT FOR WEEK COMMENCING MONDAY 27 MARCH 2017
SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street for 5 months.
Brown Street (Douglas Street to Miln Street) – closed from Monday 27 March for 5 working days for SSE cabling works.
Blackness Road / Glamis Road – temporary traffic lights for 2 weeks for gas main renewal.
Forest Park Road – temporary traffic lights for one week for Scottish Water main repair.
Milnbank Road – temporary traffic lights for one week for Scottish Water main repair.
Wright Avenue – off peak temporary traffic lights on Thursday 30 March for telecoms maintenance.
Forthcoming Roadworks
Brown Street (Guthrie Street for 35m south) – closed southbound from Monday 3 April for 5 working days for Scottish Water mains repair works.