Further to my recent update on the welcome improvements to the footways in Seafield Road, here's details of information the City Council has given to local residents:
I wish to notify you that work is programmed to commence at the above location on Monday 2 July, 2012 and will last approximately 14 days. The contractor for the works is Tayside Contracts. In the interest of public safety, and due to the nature of the works, a road closure will be implemented for both phases of the works.
Phase 1:- East/west section of Seafield Road – Nos 52 to 58. (Approx. duration – 6 days)
Phase 2:- North/south section of Seafield Road – No 66 to Roseangle (Approx. duration – 8 days)
For both phases, through traffic will be diverted via Roseangle, Bellfield Avenue and reverse for the duration of the works, with appropriate diversion signing in place for each phase.
No on-street parking will be allowed on the section of carriageway being worked on. Access to the car park to the east of No 58 Seafield Road will be maintained, and limited access to properties within the closed section will be maintained, though delays may be experienced. We would, however ask that vehicular traffic movements be kept to a minimum, where possible.
Please note that pedestrian thoroughfare will be maintained throughout the works.
Please accept my apologies for any disruption these works may cause. I am sure that you will understand that footway maintenance work is unavoidable and necessitates a degree of inconvenience to road users."